Hatch
Hatch supplies engineering, project and construction management services, process and business consulting and operational services to the mining, metallurgical, energy and infrastructure industries.
Mining & Metals Energy Infrastructure Services Technologies
 
Precious Metals Projects
 
Waterval Concentrator Retrofit Project

Waterval Concentrator Retrofit Project Anglo Platinum completed the Waterval concentrator retrofit project, as part of its current expansion and optimization drive. The plant facilities are located within the battery limits of the existing Waterval concentrator boundary, and replaced a large portion of the previous operation.

The HGN-JV team, consisting of personnel from Hatch, Grinaker-LTA Process (now E&PC) and PDNA Mining & Industrial, completed the EPCM work necessary to scope, design, and implement the program at a capital cost of R960 million. Hatch was the senior partner in the JV and the team was located in the Hatch Woodmead offices. The project replaces the crusher plant, primary milling and secondary milling sections with a modern, twin-stream primary ball milling and flotation section together with additional capacity for the scavenger flotation and a complete upgrade of the cleaner circuits.

At the same time the throughput will increase from the current 360-ktpm primary/520-ktpa regrind to 620ktpa. This requires the supply and installation of the following new major equipment:

  • Two primary ROM ball mills of size 24' x 28' EGL (7.32m x 8.53m EGL) each supplied with 2x5.2-MW motor (10.4 MW installed power per mill)
  • Eight primary mill classification screens
  • Fourteen new 70m3 tank cells for primary rougher duty
  • Six new 130-m3 tank cells for additional scavenger capacity

The project was suspended during the construction phase in January 2004 as a result of revision to the Anglo Platinum group strategy. The engineering was continued and completed by December 2004. Implementation of certain work, known as "Early Works"-Phase I, continued post-suspension.

This included the new Eskom yard and Consumer substation, upgrading the Regrind Milling faciilty, installation of additional air compressors and replacement of the Rail and Engineering Workshops, which had been demolished to make way for the new equipment.

The project was reactivate in 2006 for completion of the implementation phase and will be commissioned in July 2007.

Scope of Services
The HGN-JV scope of work includes the following:

  • Project Management of all EPCM activities
  • Basic and detailed engineering in the process, civil, structural, mechanical, piping, electrical & instrumentation disciplines
  • Capital cost and change control
  • Planning
  • Procurement of all capital equipment and contracts
  • QA/QC and Materials Control/Expediting Services
  • Construction Management and
  • Commissioning Management and Support - during cold and hot commissioning

Project Highlights

  • Completed Phase I successfully. Total capital value of R300 million
  • Successful phased upgrade and commissioning of six banks of cleaners under complex and congested brownfield conditions

Project Stats

Client:
Anglo Platinum

Location:
South Africa

Start:
January 2006

Completion:
July 2007

Cost:
ZAR960 million

See more Precious Metals
projects
>

Your Career Starts Here
Articles

See technical articles for our Mining & Mineral Processing services.


More Information

Request more information on our Precious Metals services.
Our Band of Principles